Anwendung_Fernwärme
Full-service-leverandør til central- og fjernvarme Stort udvalg af fleksible og faste rørsystemer
Stort udvalg af fleksible og faste rørsystemer

Eksempler på anvendelse til central- og fjernvarme

FLEXSTAR

  • Projekt FLEXSTAR Tyskland, 2023

    Tilslutning af en varmepumpe ved hjælp af FLEXSTAR

    Se projektet i denne video (engelsk)

     


  • FLEXSTAR biogasanlægsprojekt, Veigy-Foncenex, Frankrig, 2023 (engelsk)

    Project
    In the French twin municipality of Veigy-Foncenex, a reliable pipe system was to be laid for a biogas plant near Lake Geneva. The biogas site was founded five years ago, and a new building was added in 2023. A local heating pipeline with our FLEXSTAR UNO pipes was installed to ensure a flawless energy supply for the new part of the building. 

    Execution
    Two rings of FLEXSTAR UNO, each 200 metres long, were supplied and laid for this construction project. The aim was to connect the pre-pit of the biogas plant with the boiler room. The construction work took a total of two months, whereby the actual laying of the pipes was completed within two days.  

    The most important construction stages were the construction of a new building and the laying of the pipes under the floor slab. In the first stage, the pipes were laid in the new building before the concrete slab was poured. The next stage involved laying the trench to the boiler room. Thanks to the good weather and the easy handling of the FLEXSTAR pipes, the installation was simple and uncomplicated. Now the biogas plant can supply the region even better with renewable energy in the future. 

    Download project as PDF

     


CALPEX PUR-KING

  • CALPEX-projekt Riehen, Fondation Beyeler, Schweiz, 2023 (engelsk)

    Project
    In the canton of Basel-Stadt, an efficient pipe was laid in the village of Riehen for the Fondation Beyeler, the internationally renowned museum of modern and contemporary art. Our best-insulated CALPEX pipe was used to supply the new museum building with district heating and cooling in the future.

    Execution
    Construction work began in November 2023 and extended over three stages. A total CALPEX pipe length of approx. 800 metres was installed in the project. The aim of the work was to connect the new museum building with the pavilion and connect it to an existing district heating network. A special feature of the project was the production of a special part. This was a ventilation system, which was agreed with the customer before construction work began and installed accordingly. During the construction work, the customised part had to be slightly adjusted on site by the regional welder.

    One of the biggest challenges in the CALPEX project, in addition to the complex construction of the customised product, was the terrain next to the new museum building. In order to protect the large old trees, the pipes had to be laid carefully in the trench - which our fitters mastered in exemplary fashion.

    Download project as PDF


  • CALPEX projekt, Attiswill, Schweiz, 2018

    Projekt

    I kommunen Attiswill i Bern blev tre lejlighedskomplekser forbundet via et varmenetværk. Borgerne i lokalsamfundet leverer selv råmaterialet til centralvarmesystemet - træ fra den nærliggende skov.


    Udfordring

    Umiddelbart inden rejsegildet, skulle CALPEX røret lægges ved en temperatur omkring frysepunktet. Ekstra forholdsregler, som forvarmning af CALPEX røret, var med til at sikre, at røret kunne installeres uden problemer. Rolf Steffen, som er teamleder hos Alpiq AG er meget tilfreds, nu hvor CALPEX røret er blevet lagt succesfuldt. ”Projektet har demonstreret et velfungerende samarbejde mellem montøren, Meier Tobler, og BRUGG Rohrsystem AG lige fra planlægningsfasen og helt frem til eksekveringen. Det er præcist sådan, jeg forestiller mig et teamwork skal være.”

    Download projektet som PDF (engelsk)


CASAFLEX

  • CASAFLEX/PREMANT-projekt fjernvarmenetværk Carona, Ticino, Schweiz, 2023 (engelsk)

    Project
    In Carona, a small village in the popular Swiss canton of Ticino, an extensive district heating pipeline was laid from the heating plant to the centre of the village. Our reliable PREMANT UNO and CASAFLEX DUO pipes were used to optimise the supply of heat energy to the residents.

    Execution
    The main heating network for Carona was built twelve years ago. Over the years, it has been repeatedly extended and expanded. In the course of these expansions, the largest construction phase was completed in 2019. We laid an extensive district heating pipeline from the heating centre to the village centre. Our rigid PREMANT UNO pipe was used for the straight pipeline. The flexible and bendable CASAFLEX DUO pipe, on the other hand, was mainly used in the centre of the village.

    The biggest challenge on site was the limited space in the old town centre. As the streets were not passable by lorry, our fitters parked the lorry outside the village centre and then pulled the CASAFLEX pipe over the winding streets to the trench. The laying of the pipes themselves has been a complete success so far.

    Download project as PDF

     


  • CASAFLEX/PREMANT-projekt varmenetværk Sachseln, Schweiz, 2023 (engelsk)

    Project 
    In the diverse Swiss municipality of Sachseln, a district heating pipeline was laid near Lake Sarnersee for the local heating network. Our efficient CASAFLEX and PREMANT DUO pipes were used for the Flüelistrasse to ensure that the residents are supplied with sustainable energy in the future.  

    Execution 
    Construction work began in March 2023 and is still ongoing, as the construction project is part of a larger heating network. As a pipe constructor, we have already realised several projects for the customer together with the engineering office. The aim of this project was to connect Flüelistrasse to an existing district heating network. The energy released for the district heating pipeline is obtained from the combustion of wood chips. 

    As the Flüelistrasse connects the village of Sachseln with Flüeli-Ranft and the pilgrimage site there, it was important to minimise damage to the road. Our CASAFLEX and PREMANT DUO pipes have two inner pipes of the same size for the flow and return of thermal energy. As only one pipe was required per line instead of two, our fitters were efficient when laying the pipes. The biggest challenge in the construction project was installing the pipe at the Salzbrunnen bridge. Because the pipeline could not be installed above or below the bridge, it was necessary to attach it to the side of the Salzbrunnen bridge with special fastenings. 

    Download project as PDF

     

     


  • CASAFLEX/PREMANT-projekt Klausenstrasse, Bürglen, Schweiz, 2023 (engelsk)

    Project 
    In the popular sports and recreation centre in Bürglen, a reliable and robust local heating pipeline from BRUGG Pipes was laid for Klausenstrasse for the local community. Our perfectly matched CASAFLEX and PREMANT pipes were used in this project to provide residents with a reliable supply of sustainable energy in the future.  

    Realisation 
    Construction work began in March 2023 and lasted until July 2023. The aim was to lay a local heating pipeline for the school building and the surrounding residential buildings. The flexible CASAFLEX and the rigid PREMANT pipe system were used in several construction stages. In total, the fitters installed a route length of 400 metres during this construction phase. Approx. 1,700 metres are planned for the final expansion. 

    Important steps in this project included parking the lorry with the material, pulling and aligning the pipe in the trench and fitting the couplings. Our resistant PREMANT pipes were used for the transport line and the flexible CASAFLEX pipes were used for the house connections. A considerable challenge in the project was laying the pipeline from the power station up the steep mountainside to the main road. Despite the demanding gradient on site, our fitters mastered the individual construction stages with aplomb.  

    Download project as PDF

     


  • CASAFLEX/PREMANT-varmenetværksprojekt, Rothenthurm, Schweiz, 2023 (engelsk)

    Project 
    In the foothills of the Swiss Alps, the municipality of Rothenthurm has decided to install a district heating pipeline. Many public and private buildings in the town are to be heated sustainably with a central heat source. Our compatible CASAFLEX and PREMANT pipes were used to provide the residents with an optimum energy supply in the future. 

    Realisation 
    The construction project started in summer 2019 and involved laying a total length of up to six kilometres. Not only existing buildings, but also new flats will be connected to the heating network. Our rigid PREMANT pipes were used for long and straight sections. Flexible CASAFLEX pipes were used for the house connections.  

    In the first construction phase, the district heating pipeline was built from the new heating centre to the primary school building. The energy for the heating centre is supplied by an enormous wood boiler, in which heat is generated by burning wood chips and transported to the buildings through our pipes.  

    When carrying out the project, the trench along the roads had to be cleared in such a way that it caused as little disruption to road traffic as possible. Another challenge for the workers on the project was the electrical and water pipes already laid in the ground. The altitude of the construction site posed an additional challenge in winter, as the construction pits had to be kept clear of snow. 

     


FLEXWELL DHC

  • FLEXWELL-FHK-projekt Worblental-varmenetværk, Bern, Schweiz, 2024 (engelsk)

    Project
    We have successfully completed the expansion of the district heating network for our customer EBL (Genossenschaft Elektra Baselland) in the Swiss capital of Bern. With our extremely heavy-duty FLEXWELL DHC district heating pipeline, we have completed a crucial construction phase. Namely the connection between the municipality of Ittigen and the city of Bern. Our pipes were laid under the River Aare to supply the Worblental heating network with sustainable heat in the future.

    Execution
    The project began immediately after Easter with the delivery of two of our FLEXWELL DHC pipes in the largest available dimension DN 150, which weighed an impressive 7.5 tons per pipe. With a casing diameter of 310 millimetres, a pipe length of 226 meters each was transported to Bern on two drums. Thanks to the use of a special transport with extra width, the pipes were also transported over narrow stretches of land.

    The construction site was managed thanks to the use of heavy machinery and six experienced fitters. A special mobile crane with a lifting capacity of 130 tons was used to unload the pipes. Another 60-tonne pneumatic crane lifted the drums into the pipe-laying trolley. Two of the FLEXWELL DHC district heating pipes were pulled from the starting trench on Arastrasse in Ittigen into the empty pipes and laid from there under the river up to Tiefenaustrasse in Bern using cable winches.

    Download project as PDF


  • FLEXWELL DHC-projekt Moosstrasse, Lengnau, Schweiz, 2023 (engelsk)

    Project 
    The Burgergemeinde and the municipality of Lengnau in the Swiss canton of Bern are focussing on ecological and economical heating with their joint heating network called WärmeLengnau - with the aim of producing heat sustainably. Our durable FLEXWELL DHC steel casing pipe system was used in Moosstrasse to ensure that the town is optimally supplied with heat energy. 

    Execution
    Since 2020, many new district heating pipes from BRUGG Pipes have already been reliably laid for the construction projects of the heating network in Lengnau. In September 2023, a district heating pipe was installed in Moosstrasse as part of these construction projects. The aim was to connect the flexible steel casing pipe to an existing heating centre in the shortest possible time so that public traffic was affected as little as possible. 

    The short time frame was a considerable challenge for our fitters on site, especially as a total of two FLEXWELL DHC pipes, each 134 metres long, were to be laid. Due to the time constraints, our workers had to unwind the pipes from the reel, straighten them, pull them into the trench and align them particularly quickly and efficiently. As the trench was very close to the road, it was also important to work extremely carefully within the cordoned-off areas when laying the pipes. Another challenge was finding the space for the bogie and ensuring access for the lorry with the drum. Despite the challenges, the installation went smoothly thanks to the hard work of our fitters. 

    Download project as PDF

     


  • FLEXWELL-FHK-projekt Nürenbergstrasse, Zürich, Schweiz, 2023 (engelsk)

    Project 
    In Zurich, the city with the highest population in Switzerland, a flexible and resistant district heating pipe from BRUGG Pipes was laid for Nürenbergstrasse under narrow conditions. Our FLEXWELL DHC steel casing pipe system was used to provide the residents of the building block with an optimum and sustainable supply of heat. 

    Execution 
    The construction project began in September 2023. The aim was to connect the flexible steel casing pipe to an existing pipeline and connect it to the building. The construction work took just three days, with the most important steps being the challenging pulling of the pipe into the trench and the pipe laying itself. Two FLEXWELL DHC pipes were used for this project. As the trench was close to a garden plot, it was important to lay the pipe extremely carefully. 

    At the construction site, there was hardly any parking space on Nürenbergstrasse for the lorry carrying the material, which is why the workers parked the lorry on the other road and then pulled the pipe across a green area to the trench. Another challenge was that no tractor unit could be used for digging. The fitters on site therefore worked increasingly with deflection pulleys to align the pipes underground and master the narrow bends - which they did perfectly. 

    Download project as PDF

     


  • FLEXWELL-FHK-projektet Museum of Transport Lucerne, Schweiz, 2022 (engelsk)

    Project
    Insulated pipe systems at the Swiss Museum of Transport
    At Switzerland’s largest and most famous museum – the Swiss Museum of Transport located directly on Lake Lucerne – BRUGG Pipes collaborated on an amazing project together with Energie Wasser Luzern (ewl) in March 2022. The district heating and cooling lines connect the new energy centre of the new “House of Energy” multi-purpose building to the existing exhibition buildings through the outdoor area.

    Execution
    Use of lake water as a modern and ecological source of heating and cooling in Lucerne.
    The system is located in the outdoor area of the museum, which is also open to visitors, so fast and efficient execution of the project was of utmost importance and central for all involved parties. Thanks to detailed project planning and coordination, the project went smoothly and was completed on schedule. Installation was carried out by our own installation team to the complete satisfaction of the customer.

    A special feature of this project was that the lake water in the immediate vicinity was used as an energy source and distributed with a heat pump. The lake has large heat and cold reserves that can be used ecologically. This is an inexpensive and renewable source of energy with low investment costs and low maintenance. Thanks to the energy from the lake, the use of fossil fuels can be greatly reduced, thereby minimising CO2 emissions. Since the energy is produced locally, long transport routes are not necessary and the added value stays in the region

    Download project as PDF

     


PREMANT

  • PREMANT projekt DN 350, Sion, Schweiz, 2020

    Projekt CH-Sion  - 21 km PREMANT DN 350 rør

    Video (tysk)

     

     

     


  • PREMANT projekt, stranden ved det Baltiske Hav, Heiligendamm, Tyskland 2017

    Fjernvarme på stranden ved det Baltiske HavDe lysende hvide bygninger langs stranden ved det Baltiske Hav har givet Heiligendamm tilnavnet ”den hvide by ved havet”. ”Perlerækken” af hvide bygninger er siden 2017 blevet forsynet af en nylagt fjernvarmeledning. Både gamle og nye fjernvarmeledninger løber her - en investering på i alt €1.1 million. PSP DN 200 røret blev forbundet til det eksisterende DN 250 plastikkapperør i nærheden af den snævre Molli-jernbane. German Pipe PREMANT rør og formstøbte dele blev leveret og lagt for at dække en længde på ca. 250 m. 


    Som sædvanlig var der andre forsyningsledninger, der skulle krydses. Statisk blev røret målt til 16 bar. Det var relativt nemt at placere de beregnede U- og Z-ekspanderer langs Kühlungsborner Straße. Da der blev anvendt vinkler på 1 x 2 m, var det ikke nødvendigt med monteringsmuffer. PREMANT og FLEXWELL.
    Situationen ændrede sig mellem spabygningen og Grand Hotel. Områderne mellem de tilstødende bygninger og stier var smalle, og det viste sig nødvendigt at anvende en anden metode. Det op til 110°C varme vand, flyder her i en dybde af indtil 4 m. Med BRUGG fjernvarmeledning DHC kunne denne sektion færdiggøres ved hjælp af horisontal boring og uden at skulle grave stier, parkeringspladser og græsplæner op. Skiftet fra PREMANT til FLEXWELL var afgørende i denne situation. Som resultat af det interne tryk på 16 bar er udvidelseskraften i enderne cirka 45 kN. For at absorbere dette tryk, blev der efterfølgende foretaget en statikmåling på PREMANT rørene og de formstøbte dele. 

    Noget af trykket absorberes af overfladefriktionen, som er på omtrent 4 kN/m. Størstedelen af modtrykket opnås dog ved hjælp af sidekompressionen via PSP-vinklerne mod jorden. FLEXWELL fjernvarmeledningens stålkappe hjælper også her, da den optager eller overfører noget af modtrykket. Den tredje og fjerde sektion gik fra Villa Perle, som blev totalrenoveret i 2013, til bagsiden af Hotel Residenz. Yderligere 600 m FLEXWELL 200/310 rør blev nedgravet kun afbrudt ved forbindelses- og skæringspunkter. Nogle rør blev lukket af for at etablere forbindelse til det eksisterende PSP-rør. Seks kugleventiler i et område på blot 20 m² gør det muligt at koble til igen på et senere tidspunkt. Projektet “FWN-Aufrüstung Heiligendamm – 1. bis 4. BA” (Heiligendamm fjernvarmeopgradering - anlægsfase 1 til 4) viser, hvordan man kan skabe en optimal rørføring ved hjælp af den smarte planlægningsløsning at kombinere faste og fleksible rørsystemer. German Pipe udarbejder statikberegningerne. 

    Flowtemperatur: 110°C
    Nominelt tryk: PN 16

    Download projektet som PDF (engelsk)


Rørsystem med stålkappe

  • Projekt med rørsystem med stålkappe som dampledning i Luterbach, Schweiz

    Opgave:

    En dampledning blev monteret mellem forbrændingsanlægget og papirfabrikken. Af visuelle årsager kunne et 836 m langt mellemstykke ikke lægges over jorden, og det overjordiske rør kunne ikke lægges i jorden. Det skulle der findes en løsning på. Krav: 220°C driftstemperatur DN 500, output 45 tons/time

    Løsning:

    Der blev lagt et rør med stålkappe. Et FEXWELL DN 100 fremstillet af 1.4404 stål blev brugt til tilbageføringen af kondensvand. Der blev hovedsageligt anvendt dele på 12 m på den 836 m lange strækning. Det var nødvendigt med specialdele ved skift af retning. Det fleksible DN 100 kondensrør kunne lægges i ét stykke mellem brøndene.